Pipe ranging from 20-24 inches was installed for a major oil sands producer near Bonnyville, Alberta. The project scope included for 30 kilometers of right-of-way and 60 kilometers of pipe installation for brackish lines and emulsion lines.
Challenges on the project included the need to preheat the pipeline in order to allow it to handle hot fluids transport, as well as being working with two pipelines on same right of way.
This multi-million dollar project was successfully completed in four months.