Digging deeper and smarter

When it comes to excavations for major projects, particularly in densely developed urban areas, there are more options than just the conventional bottom-up building approach writes geotechnical specialist John Endicott.

While just about every major construction project involves digging large holes in the ground, the methods of excavation can have a significant impact on timeframes and costs. The majority of large-scale projects have opted for a conventional ‘bottom-up’ approach, but there are very powerful arguments for considering other options by using the ‘top-down’ method, or a hybrid which combines ‘bottom up’ and ‘top down’. This combined method is gaining more traction because it can be highly  competitive in cost and time.

Approaches for deep excavation explained

Bottom up – this conventional method involves first sinking temporary diaphragm walls to the required depth below ground, digging and removing soil, installing temporary steel strutting and then creating the complete hole with a concrete slab base and open to the sky. As the name suggests, the building work then rises from the concrete slab base. Necessarily, there is a lengthy period of time during the excavation in which construction cannot take place.

Top down – once again the project begins by sinking the diaphragm walls, plus central supporting ‘plunge’ columns (can be temporary or permanent), and then excavating enough of the earth to complete a ground-level slab. This slab is substantial enough to carry the weight of construction equipment including cranes, and incorporates openings though which soil can be lifted up and removed. The excavation then takes place under the ground slab, and permanent floors are cast on the way down  to the desired depth. It also means that simultaneously construction above ground can start. This is ideal for high-rise structures in constrained sites and can result in time savings that can amount to several months. Cost savings are available too because generally no steel strutting is required for wall support. Top-down construction uses the permanent structure floors to strut as the excavation is taken down in stages, floor by floor. Another use of the top-down approach is when creating new metro lines under roads. In these cases it’s possible to use the top slab to safely carry all utilities and some of the road can be reinstated until the works underneath have been completed.

Hybrid method – this is when it is appropriate and the site is large enough to incorporate both methods. The concept is that part of the site is dedicated to a top-down approach while the rest is built from the bottom upwards.

Compare and contrast

Top-down approach

Advantages

Disadvantages

· This offers very quick site coverage which includes a robust working platform.

· For large sites, openings can be provided in the floors at many locations within the site and not just around the perimeter.

· For smaller sites, the ground floor structure provides a site working area and a temporary steel decking is not required.

· Requires little or no temporary steel shoring – producing good cost savings.

· Requires no formwork for floors or roof with significant savings in cost and time

· Cheaper to construct.

· Multiple accesses made possible through the voids in the slab and not limited to around the perimeter.

· For combined development that includes a substantial structure above ground, the top-down approach makes it possible to get an early start on construction.

· For sites of irregular shape, floor slabs are more versatile and therefore are more efficient than using steel strutting

· Because work needs to be carried out through openings in the slab, access is only via the openings below the slabs during excavation.

· When building multiple stories above ground, this approach requires the construction of strong foundations and plunge piles

· In the case of very tall buildings, this approach requires complex design work – for example it may require plunge piles  sufficient to support the first 10 floors above ground, but then more work will be required to create more substantial foundations for floors above the first 10.

· Waterproofing cannot be installed outside the diaphragm walls.

Bottom-up approach

Advantages

Disadvantages

· Design is easier and therefore design costs are lower than for the top-down approach, and a bottom-up approach is quicker to design.

· Heavy foundations, such as large piled foundations for the high rise are required and are generally installed from the ground surface before excavation for top down and for bottom up.

· Waterproofing can be installed around the whole outside, including the outside the permanent walls.

· Access for cranes is not restricted up and down the sides of the excavation. For sites large enough to have a perimeter area to accommodate construction equipment, and when the excavation is not wide then this method is quicker than the top-down approach. An example here is that some metro stations have a large site area outside that is handed back for other uses.

· Construction  is usually slower and more expensive than the top-down approach.

· It is not possible to carry out simultaneous upwards and downwards construction until the bottom of the basement is concreted.

· Cranes can be located only on firm ground outside the excavation or on heavy-capacity temporary decks within the excavated area. For wide sites cranes may not be able to reach the middle of the excavation, whereas the top-down method can provide openings at many locations across the site area.

· For very deep projects, the thickness of the temporary walls plus the permanent walls is greater than for the top-down method using diaphragm walls plus skin wall. Therefore, bottom-up working needs more space for the combined walls or the finished floor area is smaller.

· The temporary walls serve little or no purpose after completion and, therefore, are wasted.

· If the scheme design is for bottom-up construction, the time for tendering might be longer since contractors need to prepare a tender design.

Wan Chai Development Phase II –Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

On the harbor front of Wan Chai, this project incorporated top-down and bottom-up construction methods for a road tunnel beneath the convention and exhibition centre.

Here the restraint of very limited working and storage space available, phased landfill, diaphragm-wall / pile installation, excavation and complex permanent tunnel and pile arrangements, meant that the construction method adopted needed to optimize the construction process.

A top-down approach was chosen for the shallow portion of the tunnel for the western Stage 1 zone.

A bottom-up approach was selected for stages 2 amd 3 where the tunnel dives deeper towards the east.

The benefits of this approach include –

  • A cost-saving design of the permanent road tunnel, eliminating the need of rock socketed diaphragm wall and barrettes foundation.
  • An in-situ tunnel box design which is more durable and watertight in the longer term.
  • A cost-effective temporary diaphragm wall design with significantly shorter toe levels sufficient for water cut-off, replacing the original rock socketed diaphragm wall design.
  • Rock socketed H-piles used as king post at temporary construction stage, saving cost of providing additional support to the Excavation and lateral support system.

MORE FROM THIS AUTHOR